File #: 24-5785   
Type: Orange County Local Transportation Authority Item Status: Reported to Board - Consent
File created: 9/6/2024 In control: Regional Transportation Planning Committee
On agenda: 11/4/2024 Final action:
Title: Amendment to Cooperative Agreement with the California Department of Transportation for the Interstate 5 Improvement Project Between State Route 73 and Oso Parkway
Sponsors: Niall Barrett, James G. Beil
Attachments: 1. Transmittal, 2. Staff Report, 3. Attachment A, 4. Attachment B

Subject

title

Amendment to Cooperative Agreement with the California Department of Transportation for the Interstate 5 Improvement Project Between State Route 73 and Oso Parkway

overview

Overview

On October 22, 2018, the Orange County Transportation Authority Board of Directors approved a cooperative agreement between the Orange County Transportation Authority and the California Department of Transportation for construction capital and construction support services for the Interstate 5 Improvement Project between State Route 73 and Oso Parkway as part of the Interstate 5 Improvement Project between State Route 73 and El Toro Road. An amendment to the existing cooperative agreement is needed to provide additional funding for construction capital and construction support services.  

 

recommendation

Recommendation(s)

A.                     Authorize the Chief Executive Officer to negotiate and execute Amendment No. 3 to Cooperative Agreement No. C-8-1960 between the Orange County Transportation Authority and the California Department of Transportation, in the amount of $3,929,113, for additional construction capital and construction support services for the Interstate 5 Improvement Project between State Route 73 and Oso Parkway. This will increase the maximum cumulative obligation of the cooperative agreement to a total contract value of $157,942,113.

 

B.                     Authorize the use of up to $3,929,113 in Measure M2 funds for the construction phase of the Interstate 5 Improvement Project between State Route 73 and Oso Parkway.

 

C.                     Authorize staff to process all necessary amendments to the Federal Transportation Improvement Program and execute or amend all necessary agreements to facilitate the above actions.