3.
Contract Change Order Related to the Design and Construction of Area 3 for the
Coastal Rail Stabilization Priority Project
Jason Lee/James G. Beil
Overview
On April 14, 2025, the Orange County Transportation Authority Board of Directors adopted
Emergency Resolution No. 2025-025 which authorized the Chief Executive Officer to enter
into Agreement No. C-5-4033 with Condon-Johnson & Associates, Inc. for the design and
construction of Area 3 of the Coastal Rail Stabilization Priority Project. A contract change
order is required to address additional design requirements and construction work
associated with the pedestrian trail fence included in the Mariposa Beach access
improvements.
Recommendation(s)
Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No.
13 to Agreement No. C-5-4033 with Condon-Johnson & Associates, Inc., in the amount of
$321,437, for the redesign and construction of the pedestrian trail fence.
Attachments:
4.
Comprehensive Transportation Funding Programs -
Projects Programming Recommendations
Mason Dosher/Rose Casey
Project X Tier 1 2026 Call for
Overview
The Orange County Transportation Authority issued the 2026 annual Measure M2
Comprehensive Transportation Funding Programs Environmental Cleanup Program Tier 1
call for projects in March 2026, which provides funding for water quality improvement
projects to address transportation-generated pollution. Project applications were due in
May 2026. A list of projects recommended for funding is presented for Board of Directors’
review and approval.
Recommendation(s)
A.
Approve the award of $3,870,044 in Tier 1 Environmental Cleanup Program funding
for eight projects.
B.
Approve an exception to the Comprehensive Transportation Funding Programs
guidelines to allow the City of Huntington Beach to (1) be recommended for a
Measure M2 funding allocation while the City of Huntington Beach is temporarily
ineligible to receive Measure M2 funds, and (2) proceed with the project, at its own
risk, prior to the issuance of a letter agreement. If the City of Huntington Beach
regains Measure M2 eligibility and all applicable requirements are satisfied, the
Orange County Transportation Authority shall enter into a letter agreement and
provide the awarded Measure M2 funds for the project.
Attachments: