Title
Amendment to Cooperative Agreement with the California Department of Transportation for the Interstate 5 Improvement Project from Oso Parkway to Alicia Parkway
Overview
Overview
On February 12, 2018, the Orange County Transportation Authority Board of Directors approved a cooperative agreement between the Orange County Transportation Authority and the California Department of Transportation to provide construction capital and construction support services for the Interstate 5 Improvement Project from Oso Parkway to Alicia Parkway as part of the Interstate 5 Improvement Project between State Route 73 and El Toro Road. Board of Directors’ approval is requested to amend the cooperative agreement for additional funding for construction capital and construction support services.
Recommendation(s)
Recommendations
A. Authorize the Chief Executive Officer to negotiate and execute Amendment No. 4 to Cooperative Agreement No. C-8-1426 between the Orange County Transportation Authority and the California Department of Transportation, in the amount of $23,660,000, for additional construction capital and construction support services for the Interstate 5 Improvement Project from Oso Parkway to Alicia Parkway. This will increase the maximum cumulative obligation of the cooperative agreement to a total contract value of $196,456,000.
B. Authorize the use of up to $23,660,000 in Measure M2 funds for the construction phase of the Interstate 5 Improvement Project from Oso Parkway to Alicia Parkway.
C. Authorize staff to process all necessary amendments to the Federal Transportation Improvement Program and execute or amend all necessary agreements to facilitate the above actions.