File #: 21-3481   
Type: Orange County Local Transportation Authority Item Status: Passed
File created: 6/2/2021 In control: Regional Transportation Planning Committee
On agenda: 9/2/2021 Final action: 9/13/2021
Title: Capital Programming Update
Sponsors: Ben Ku, Kia Mortazavi
Indexes: M2
Attachments: 1. Transmittal, 2. Staff Report, 3. Attachment A, 4. Attachment B, 5. Attachment C, 6. Attachment D
Title
Capital Programming Update

Overview
The Orange County Transportation Authority uses various funding sources to implement planning efforts, capital projects, and transit operations. Project costs can vary from the programmed amount in response to changing circumstances, which may require funding revisions. Board of Directors' authorization is required to provide funding for current or planned freeway, grade separation, and transit capital projects.

Recommendation(s)
A. Consistent with right-of-way phase estimates for the Interstate 5 Improvement Project from Yale Avenue to State Route 55 (Segment 2), authorize the use of $23.926 million from the following fund sources:

* Surface Transportation Block Grant ($17.5 million),
* Measure M2 freeway funds ($5.575 million),
* Repurposed earmarks (up to $0.851 million), contingent on Federal Highway Administration approval, and
* Additional Measure M2 freeway funds in lieu of $0.851 million of repurposed earmarks, in the event the federal funds are not available.

B. Consistent with updated design phase estimates for the State Route 55 Improvement Project from Interstate 5 to State Route 91, authorize the use of the funding below, increasing total funding for the phase from $8.921 million to $11 million, and reducing Measure M2 funds by $3.921 million:

* Surface Transportation Block Grant ($3.359 million), and
* Highway Infrastructure Program ($2.641 million).

C. Authorize the use of $1.720 million in Measure M2 for the State Route 55 Improvement Project from Interstate 405 to Interstate 5 to support anticipated increased costs for the design phase, changing the total project estimated cost from $504 million to $505.720 million.

D. Consistent with the forecasted cost for the environmental phase for the Interstate 5 Managed Lanes Project from the Orange County/San Diego County line to Avenida Pico, authorize the use of $0.907 million in additional Surface Transportation Block Grant funds to fund this chan...