Title
Contract Change Orders for Over-Excavation of Unsuitable Soils and Utility Conflicts for the Construction of the OC Streetcar Project
Overview
On September 24, 2018, the Orange County Transportation Authority Board of Directors approved Agreement No. C-7-1904 with Walsh Construction Company II, LLC, for construction of the OC Streetcar project. Contract change orders are required for work to address over-excavation of unsuitable soils and utility conflicts.
Recommendation(s)
A. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 52.1 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $540,000, for over-excavation of unsuitable soils for the construction of the OC Streetcar project.
B. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 4.3 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $2,000,000, for work to address utility conflicts for the construction of the OC Streetcar project.