Skip to main content
OCTA header

Public Comments
Public comments may be submitted pursuant to the instructions noticed in the meeting agenda, which will be available at least 72 hours prior to the meeting.

Live and Archived Audio
NEW: Listen to the live and recorded Board and Committee meetings in the "Video/Audio" column below.

 
File #: 20-3010   
Type: Orange County Local Transportation Authority Item Status: Passed
File created: 10/16/2020 In control: Transit Committee
On agenda: 3/11/2021 Final action: 3/11/2021
Title: OC Streetcar Project Supplemental Contingency
Sponsors: Mary Shavalier, James G. Beil
Attachments: 1. Transmittal, 2. Staff Report, 3. Attachment A, 4. Attachment B, 5. PowerPoint

Title

OC Streetcar Project Supplemental Contingency

 

Overview

The Orange County Transportation Authority is currently underway with the implementation of the OC Streetcar project. Board of Directors’ approval is requested to provide additional funding to supplement the contingency for the project.

 

Recommendation(s)

A.                     Authorize the use of up to an additional $7.32 million in Measure M2 funds and up to $8.29 million in additional Federal Congestion Mitigation and Air Quality Improvement Program funds to supplement the contingency for the OC Streetcar project. Along with other previously-approved funding adjustments of $70,000, this will increase the Federal Transit Administration Full Funding Grant Agreement funding from $407.76 million to $423.44 million, with use of federal funds contingent on Federal Transit Administration approval. 

 

B.                     Authorize staff to process all necessary amendments to the Federal Transportation Improvement Program and execute or amend all necessary agreements to facilitate the above action.