File #: 20-2882   
Type: Orange County Local Transportation Authority Item Status: Passed
File created: 8/5/2020 In control: Transit Committee
On agenda: 9/10/2020 Final action: 9/10/2020
Title: Contract Change Order for Vapor Barrier Installation for the Construction of the OC Streetcar Project
Sponsors: Mary Shavalier, James G. Beil
Attachments: 1. Transmittal, 2. Staff Report, 3. Attachment A

Title

Contract Change Order for Vapor Barrier Installation for the Construction of the OC Streetcar Project

 

Overview

On September 24, 2018, the Orange County Transportation Authority Board of Directors authorized Agreement No. C-7-1904 with Walsh Construction Company II, LLC, for construction of the OC Streetcar project. A contract change order is required to install a vapor barrier under the foundation of the maintenance and storage facility.

 

Recommendation(s)

Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 9 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $395,717, for installation of a vapor barrier under the maintenance and storage facility.