Title
Agreement for the Construction of the Right-of-Way Slope Stabilization Project
Overview
The Orange County Transportation Authority’s Board of Directors approved the construction of the right-of-way slope stabilization project as part of the Orange County Transportation Authority’s Fiscal Year 2017-18 Budget. Bids were received in accordance with the Orange County Transportation Authority’s public works procurement procedures. Board of Directors’ approval is requested to execute an agreement with the lowest responsive, responsible bidder.
Recommendation(s)
A. Find James McMinn, Inc., the apparent low bidder, as non-responsive due to failure to meet the federal requirement for Disadvantaged Business Enterprise participation.
B. Authorize the Chief Executive Officer to negotiate and execute Agreement No. C-7-2047 between the Orange County Transportation Authority and Bosco Constructors, Inc., the lowest responsive, responsible bidder, in the amount of $1,735,600, for construction of the right-of-way slope stabilization project.