Title
Contract Change Order for Utility Conflicts for the Construction of the OC Streetcar Project
Overview
On September 24, 2018, the Orange County Transportation Authority Board of Directors approved Agreement No. C-7-1904 with Walsh Construction Company II, LLC, for construction of the OC Streetcar project. A contract change order is required for necessary work to address continuing utility conflicts.
Recommendation(s)
Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 4.2 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $2,426,000, for work to address utility conflicts for the construction of the OC Streetcar project.