File #: 22-4027   
Type: Orange County Local Transportation Authority Item Status: Passed
File created: 2/10/2022 In control: Regional Transportation Planning Committee
On agenda: 6/6/2022 Final action: 6/13/2022
Title: Cooperative Agreement with the California Department of Transportation for the Interstate 5 Improvement Project Between Yale Avenue and State Route 55 and Authority to Acquire Right-of-Way
Sponsors: Niall Barrett, James G. Beil
Indexes: CONTRACT, M2
Attachments: 1. Transmittal, 2. Staff Report, 3. Attachment A

Title

Cooperative Agreement with the California Department of Transportation for the Interstate 5 Improvement Project Between Yale Avenue and State Route 55 and Authority to Acquire Right-of-Way

 

Overview

The Orange County Transportation Authority proposes to enter into a cooperative agreement with the California Department of Transportation to define roles, responsibilities, and funding obligations for right-of-way support services, right-of-way engineering, right-of-way acquisition, and utility relocation for the Interstate 5 Improvement Project between Yale Avenue and State Route 55.

 

Recommendation(s)

A.                     Authorize the Chief Executive Officer to negotiate and execute Cooperative Agreement No. C-2-2232 between the Orange County Transportation Authority and the California Department of Transportation, in the amount of $1,230,000, to perform right-of-way services for the Interstate 5 Improvement Project between Yale Avenue and State Route 55.

 

B.                     Authorize the use of up to $22,706,000 in federal Surface Transportation Block Grant and Measure M2 funding for right-of-way capital and right-of-way services for the Interstate 5 Improvement Project between Yale Avenue and State Route 55.

 

C.                     Authorize staff to process all necessary amendments to the Federal Transportation Improvement Program and execute or amend all necessary agreements to facilitate the above actions.

 

D.                     Authorize the Chief Executive Officer to initiate discussions with property owners and utility owners, make offers, and execute agreements for the acquisition of all necessary real property interests and necessary utility relocations.