Title: Measure M2 2026 Update: Next 10 Delivery Plan
Sponsors: Francesca Ching, Rose Casey
Attachments: 1. Staff Report, 2. Attachment A, 3. Attachment B, 4. Attachment C, 5. Presentation

Subject

title

Measure M2 2026 Update: Next 10 Delivery Plan

overview

Overview

The Measure M2 Next 10 Delivery Plan provides a strategic framework for delivering Measure M2 freeway, streets and roads, transit, and environmental projects and programs. Staff has prepared the 2026 update of the Measure M2 Next 10 Delivery Plan, which incorporates the most recent Measure M2 sales tax revenue forecast, current external funding assumptions, and refined project schedules and costs. This update confirms that the Measure M2 Transportation Investment Plan remains deliverable through 2041 and outlines approximately $6.4 billion in planned transportation investments, inclusive of debt service payments, through fiscal year 2035-36, while continuing to closely monitor the financial sustainability of Metrolink service. The draft 2026 update is presented to the Orange County Transportation Authority Board of Directors for review and adoption.

recommendation

Recommendation(s)

A.                     Adopt the 2026 Measure M2 Next 10 Delivery Plan.

 

B.                     Direct staff to continue working with Metrolink and other member agencies to align service levels and costs with available funding to maintain financially sustainable Metrolink service through 2041.

 

C.                     Direct staff to continue monitoring revenue and project cost shifts that could affect the Measure M2 Next 10 Delivery Plan and, if necessary, report to the Orange County Transportation Authority Board of Directors with recommended adjustments.