File #: 26-6627   
Type: Orange County Transportation Authority Item Status: Passed
File created: 1/6/2026 In control: Regional Transportation Planning Committee
On agenda: 3/2/2026 Final action: 3/2/2026
Title: Agreement for the Harbor Boulevard Transit Signal Priority Deployment
Sponsors: Alicia Yang, Rose Casey
Attachments: 1. Transmittal, 2. Staff Report, 3. Attachment A, 4. Attachment B, 5. Attachment C

Subject

title

Agreement for the Harbor Boulevard Transit Signal Priority Deployment

overview

Overview

On October 13, 2025, the Orange County Transportation Authority Board of Directors approved the release of a request for proposals to initiate a competitive procurement process to retain consultant services for the deployment of a transit signal priority solution that includes software, signal equipment, and system integration. The Harbor Boulevard Transit Signal Priority Deployment project will focus on the OC Bus Rapid Route 543 and will encompass 52 signalized intersections along Harbor Boulevard. Board of Directors’ approval is requested to select a firm to perform the required work.

recommendation

Recommendation(s)

A.                     Approve the selection of Arcadis U.S., Inc. as the firm to deliver the Harbor Boulevard Transit Signal Priority Deployment.

 

B.                     Authorize the Chief Executive Officer to negotiate and execute Agreement No. C250014 between the Orange County Transportation Authority and Arcadis U.S., Inc., in the amount of $2,032,849, for a five-and-one-half-year term, to deliver the Harbor Boulevard Transit Signal Priority Deployment.