Contract Change Orders Related to the Design and Construction of Area 3 for the Coastal Rail Stabilization Priority Project
overview
Overview
On April 14, 2025, the Orange County Transportation Authority Board of Directors adopted Emergency Resolution No. 2025-025, which authorized the Chief Executive Officer to enter into Agreement No. C-5-4033, with Condon-Johnson & Associates, Inc. for the design and construction of Area 3 of the Coastal Rail Stabilization Priority Project. Contract change orders are required to address additional work associated with unforeseen subsurface conditions encountered during construction and address additional loading requirements for the construction of the Mariposa Pedestrian Bridge.
recommendation
Recommendation(s)
A. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 10 to Agreement No. C-5-4033 with Condon-Johnson & Associates, Inc., in the amount of $383,503, for unforeseen subsurface conditions.
B. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 11 to Agreement No. C-5-4033 with Condon-Johnson & Associates, Inc., in the amount of $681,067, for the loading requirements for the construction of the Mariposa Pedestrian Bridge.