Adopt Resolution No. 2025-025 and Authorize the Chief Executive Officer to Take all Necessary Actions to Address the Emergency Need for Railroad Track Stabilization in the Vicinity of Mile Post 203.83 to 204.40 and 206.10 to 206.70 on the Orange Subdivision
overview
Overview
The four reinforcement areas identified in the Coastal Rail Resiliency Study adjacent to the Orange County Transportation Authority-owned railroad right-of-way, in the vicinity of Mile Post 203.83 to 204.40 and 206.10 to 206.70 on the Orange Subdivision, have continued to experience coastal erosion and the hillside continues to move incrementally, posing an imminent threat to the railroad corridor and public safety if immediate necessary actions are not taken to mitigate the threat. Measures must be taken immediately to stabilize the track and maintain passenger and freight rail service.
recommendation
Recommendation(s)
A. Adopt Resolution No. 2025-025 and authorize the Chief Executive Officer to take all necessary actions to address the emergency need for railroad track stabilization in the vicinity of Mile Post 203.83 to 204.40 and 206.10 to 206.70 on the Orange Subdivision, and to return to the Board of Directors, as required, to report on the status thereof.
B. Authorize the Chief Executive Officer to take any and all necessary actions in regard to agreements with partner public agencies to address the emergency need for railroad track stabilization in the vicinity of Mile Post 203.83 to 204.40 and 206.10 to 206.70 on the Orange Subdivision.
C. Amend the Orange County Transportation Authority’s Fiscal Year 2024-25 Budget by $135,000,000, to accommodate the additional budget needed for the Coastal Rail Stabilization Priority Project.