Contract Change Orders for Construction of the OC Streetcar Project
overview
Overview
On September 24, 2018, the Orange County Transportation Authority Board of Directors authorized Agreement No. C-7-1904 with Walsh Construction Company II, LLC, for construction of the OC Streetcar Project. Contract change orders are required for the storage of traction power substations, additional traffic control, and to complete finishes in various areas at the maintenance and storage facility.
recommendation
Recommendation(s)
A. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 83.1 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $400,000, for the storage of traction power substations.
B. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 157.2 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $150,000, for additional traffic control.
C. Authorize the Chief Executive Officer to negotiate and execute Contract Change Order No. 260.1 to Agreement No. C-7-1904 with Walsh Construction Company II, LLC, in the amount of $120,000, to complete finishes in various areas in the maintenance and storage facility.