File #: 25-6405   
Type: Orange County Local Transportation Authority Item Status: Committee Ready - Consent
File created: 10/7/2025 In control: Transit Committee
On agenda: 11/13/2025 Final action:
Title: Consultant Selection for Construction Management Services for the Inland Slope Rehabilitation Phase II Project
Sponsors: Jason Lee, James G. Beil
Attachments: 1. Staff Report, 2. Attachment A, 3. Attachment B, 4. Attachment C, 5. Attachment D

Subject

title

Consultant Selection for Construction Management Services for the Inland Slope Rehabilitation Phase II Project

overview

Overview

The Orange County Transportation Authority Board of Directors approved the construction of the Inland Slope Rehabilitation Phase II Project as part of the Orange County Transportation Authority Fiscal Year 2025-26 Budget. On November 18, 2024, a request for proposals was released for construction management services. Board of Directors’ approval is requested for the selection of a firm to perform the required work.

recommendation

Recommendation(s)

A.                     Approve the recommended selection of Fulcrum Consultants, Inc. as the firm to provide construction management services for the Inland Slope Rehabilitation Phase II Project.

 

B.                     Authorize the Chief Executive Officer to negotiate and execute Agreement No. C-4-2582 between the Orange County Transportation Authority and Fulcrum Consultants, Inc., in the amount of $624,802, to provide construction management services for the Inland Slope Rehabilitation Phase II Project.