File #: 25-6262   
Type: Orange County Transportation Authority Item Status: Committee Ready - Regular Calendar
File created: 5/21/2025 In control: Finance and Administration Committee
On agenda: 9/10/2025 Final action:
Title: 241/91 Express Connector Project Approval
Sponsors: Kirk Avila
Attachments: 1. Staff Report, 2. Attachment A, 3. Attachment B, 4. Attachment C, 5. Presentation

Subject

title

241/91 Express Connector Project Approval

overview

Overview

In October 2019, the Orange County Transportation Authority Board of Directors approved a term sheet that provides the foundation for advancing the tolled 241/91 Express Connector Project. Since 2019, staff from the California Department of Transportation, Foothill/Eastern Transportation Corridor Agency, Orange County Transportation Authority, and Riverside County Transportation Commission have been meeting regularly to advance the project to construction. After several years of discussion, the agencies have negotiated a master agreement and operating agreement that are consistent with the term sheet. These agreements are presented for Board of Directors’ approval.

recommendation

Recommendation(s)

A.                      Authorize the Chief Executive Officer to finalize and execute a master agreement with the California Department of Transportation, Foothill/Eastern Transportation Corridor Agency, and Riverside County Transportation Commission for the development and operation of the 241/91 Express Connector Project.

 

B.                     Authorize the Chief Executive Officer to finalize and execute an operating agreement with the Foothill/Eastern Transportation Corridor Agency and Riverside County Transportation Commission for the operation of the 241/91 Express Connector Project.

 

C.                      Authorize the Chief Executive Officer to finalize and execute amendments to the Lease Agreement Regarding State Route 91 Median Improvements, Amended and Restated Development Franchise Agreement, and any other related 91 Express Lanes agreements necessary for the development and operation of the 241/91 Express Connector Project.

 

D.                     Approve the required AB 194 (Chapter 687, Statutes of 2015) consent letter for the 241/91 Express Connector Project.